04CBuildout· as of 2026-10-15

AI compute deals

Who is buying the gigawatts. 100 contracts for AI computing capacity, 2023-01-23 to 2026-10-06: cloud capacity, chip supply, data-center leases and builds, the financing behind them, and power. Each deal carries its dated public sources.

Largest stated value

$500B

OpenAI and Stargate Project (2025-01-21), investment

With a stated dollar value

59 of 100

The rest state capacity, chips or terms only

Figures from a party

89 of 100

Headline terms stated by a party to the deal

Press reports only

10

No party confirmed the deal

Every deal in the ledger

Compiled 2026-10-15. Sort by any column; open Details for each deal’s terms, later changes and dated sources. A stated value is not like-for-like: the line under it says what kind of figure it is.

AI compute deals
Google
Details for Google and Constellation Energy, 2026-10-06

Google agreed to fund uprates at 11 Constellation nuclear units in Illinois, Pennsylvania and New Jersey that add 890 MW to the PJM grid, under a 20-year deal that also includes a separate 15-year supply agreement for 2,700 MW from Constellation's existing PJM fleet; Constellation put its new investment at more than $4.3 billion.

Term: 20 years.

Constellation Energy—890 MWSigned
CoreWeave
Details for CoreWeave and AdaniConneX, 2026-10-06

CoreWeave entered India with a 240 MW AI cloud deployment at AdaniConneX data centers.

AdaniConneX—240 MWAnnounced
Anthropic
Details for Anthropic and Broadcom, 2026-10-01

Reuters reported, citing Anthropic's confidential IPO filing, that Broadcom agreed to lend Anthropic up to $42 billion to lease its chips. Broadcom did not comment and Anthropic declined to comment.

Stated as “up to $42 billion”.

Related: Anthropic and Broadcom (2025-12-11).

Broadcom$42Bpress-reported—Reported
Anthropic
Details for Anthropic and Akamai, 2026-09-24

Akamai expanded its relationship with Anthropic to $11.6 billion of contractual commitment over seven years for Anthropic's CPU workloads on Akamai Cloud, with room to grow by up to $9 billion more. Akamai issued Anthropic a warrant for up to about 5% of its stock that vests as the commitment expands.

Term: 7 years. Stated as “$11.6 billion of contractual commitment over seven years”.

Akamai$11.6Bcontract value—Signed
Anthropic
Details for Anthropic and Lambda, 2026-08-31

Reuters reported, citing a source, that Anthropic signed a $35 billion cloud deal with NVIDIA-backed Lambda for about 350 MW at a data center Hut 8 is developing in Nueces County, Texas. Neither company announced the deal.

With Hut 8, NVIDIA. Stated as “worth $35 billion”.

Related: Anthropic and Nscale (2026-08-26); Microsoft and Lambda (2025-11-03); Anthropic (reported) and Volta Infra (2026-08-04).

Lambda$35Bpress-reported350 MWReported
Anthropic
Details for Anthropic and Nscale, 2026-08-26

Press reports, led by Bloomberg, said Anthropic agreed to spend about $45 billion over six years renting about 460 MW of NVIDIA Vera Rubin capacity at Nscale's Monarch campus in West Virginia, a site Microsoft had earlier signed a letter of intent for and then left. The companies did not announce the customer or terms.

Chips: NVIDIA Vera Rubin. Term: 6 years. Stated as “$45B over six years”.

Related: Anthropic and Lambda (2026-08-31); Microsoft and Nscale (2025-10-15); Anthropic (reported) and Volta Infra (2026-08-04).

Nscale$45Bpress-reported460 MWReported
OpenAI
Details for OpenAI and SB Energy, 2026-08-17

SB Energy will build, own and operate an AI campus in Pike County, Ohio under a 20-year lease to OpenAI, starting with 4.25 GW of IT load and up to about 8 GW if NVIDIA exercises an option, and the site will host NVIDIA systems. NVIDIA provided lease guarantees capped at $105 billion for the initial 4.25 GW and agreed to invest $1.5 billion in SB Energy.

With NVIDIA, SoftBank Group. Term: 20 years. Stated as “NVIDIA's aggregate payment obligation is cumulatively capped at $105 billion for its initial commitment”.

Related: OpenAI and SB Energy (2026-01-09); OpenAI and NVIDIA (2025-09-22).

SB Energyup to $105B4.25 GWSigned
Anthropic (reported)
Details for Anthropic (reported) and Volta Infra, 2026-08-04

Volta Infra said it signed a $10 billion contract with an unnamed AI company for cloud capacity in Europe alongside Bitdeer; Bloomberg reported the customer is Anthropic and that the six-year deal covers a 133 MW Bitdeer data center in Norway with NVIDIA Vera Rubin chips. Anthropic declined to comment.

With Bitdeer. Chips: NVIDIA Vera Rubin. Term: 6 years. Stated as “a $10 billion contract”.

Related: Anthropic and Nscale (2026-08-26); Anthropic and Lambda (2026-08-31).

Volta Infra$10Bcontract value133 MWSigned
Meta
Details for Meta and BlackRock, 2026-07-28

Meta and BlackRock formed a venture, 80% owned by BlackRock funds and 20% by Meta, to develop and own Meta's 1 GW El Paso, Texas data center campus, with about $14 billion in total development costs. Meta leases the whole campus on a four-year initial term with options extending to a potential 20 years.

With Global Infrastructure Partners, HPS Investment Partners. Term: 4 years. Stated as “approximately $14 billion in total development costs”.

Related: Meta and Blue Owl Capital (2025-10-21).

BlackRock$14Binvestment1 GWSigned
Anthropic
Details for Anthropic and AMD, 2026-07-22

AMD and Anthropic agreed that Anthropic will deploy up to 2 GW of AMD Instinct MI450 Series GPUs in Helios racks, with the first gigawatt starting in the first half of 2027. AMD committed to a strategic equity investment of up to $5 billion in Anthropic; no purchase value was disclosed.

Chips: AMD MI450, AMD MI455X. Starts 2027. Stated as “a strategic equity investment of up to $5 billion in Anthropic”.

Related: OpenAI and AMD (2025-10-06); Meta and AMD (2026-02-24).

AMDup to $5B2 GWSigned
OpenAI
Details for OpenAI and Georgia Power, 2026-07-22

OpenAI announced Project Camellia, a data center it is designing and developing itself in Effingham County, Georgia, and said it is contracting with Georgia Power for 3.2 GW of power delivered in phases from 2028 to 2032.

Starts 2028.

Georgia Power—3.2 GWAnnounced
Anthropic
Details for Anthropic and TeraWulf, 2026-07-06

TeraWulf signed a 20-year lease with Anthropic for a purpose-built AI campus of about 401 MW of critical IT load at its Justified Data site in Hawesville, Kentucky, expected to generate about $19 billion over the initial term, with first capacity in the second half of 2027. TeraWulf also agreed to sell its stake in the Abernathy, Texas joint venture to a Fluidstack-led group.

Term: 20 years. Starts 2027. Stated as “approximately $19 billion of contracted revenue over the initial lease term”.

Related: Anthropic and Hut 8 (2025-12-17); Anthropic and Fluidstack (2025-11-12).

TeraWulf$19Bcontract value401 MWSigned
SK Group
Details for SK Group and NVIDIA, 2026-07

SK Group and NVIDIA signed letters of intent for a partnership described as worth more than $500 billion, covering SK Telecom's planned 2 GW AI cloud in South Korea on NVIDIA's DSX AI factory platform and Vera Rubin systems, and long-term SK hynix HBM supply and co-development. The figure is an aggregate scope, not a disclosed purchase commitment; the first AI factory is expected in 2027.

With SK Telecom, SK hynix. Chips: NVIDIA Vera Rubin. Starts 2027. Stated as “a strategic partnership worth more than $500 billion”.

Related: OpenAI and Samsung Electronics (2025-10-01).

NVIDIA$500Bestimate2 GWAnnounced
NVIDIA
Details for NVIDIA and Sharon AI, 2026-06-08

Sharon AI signed a six-year Master Cloud Services Agreement with NVIDIA, worth up to $4.88 billion, to build 72 MW of new AI data center capacity in Australia with up to 40,000 GB300 GPUs under a revenue-sharing and credit-support model. It reported the deal as $4.9 billion of its roughly $8.8 billion total contract value in August 2026.

Chips: NVIDIA GB300. Term: 6 years. Stated as “a contract value of up to $4.88 billion”.

Related: NVIDIA and IREN (2026-05-07); NVIDIA and Lambda (2025-09).

Sharon AIup to $4.88B72 MWSigned
Google
Details for Google and SpaceX, 2026-06-05

SpaceX disclosed a Cloud Service Agreement under which Google pays $920 million per month from October 2026 through June 2029 for compute including about 110,000 NVIDIA GPUs, with a reduced fee during the ramp. Google may terminate or take fewer GPUs if SpaceX misses the September 30, 2026 delivery target, and either party may terminate on 90 days' notice after 2026.

With xAI. Starts 2026-10. Stated as “$920 million per month from October 2026 through June 2029”.

Related: Anthropic and SpaceX (2026-05-06); xAI and NVIDIA (2024-10-28).

SpaceX—110,000 NVIDIA GPUs (approximately)Signed
NVIDIA
Details for NVIDIA and IREN, 2026-05-07

IREN signed a five-year contract to provide NVIDIA with managed GPU cloud services for NVIDIA's internal AI and research work, worth about $3.4 billion, using air-cooled Blackwell systems in about 60 MW of its Childress, Texas data centers.

With Mirantis. Chips: NVIDIA Blackwell. Term: 5 years. Stated as “approximately $3.4 billion”.

Related: Microsoft and IREN (2025-11-03); NVIDIA and Lambda (2025-09); NVIDIA and Sharon AI (2026-06-08); IREN and NVIDIA (2026-05-07).

IREN$3.4Bcontract value60 MWSigned
IREN
Details for IREN and NVIDIA, 2026-05-07

NVIDIA and IREN announced plans to deploy up to 5 GW of NVIDIA DSX-aligned AI infrastructure across IREN's sites, with its 2 GW Sweetwater campus in Texas as the flagship, and NVIDIA took a five-year right to buy up to 30 million IREN shares at $70 each, about $2.1 billion.

Stated as “a five-year right to buy up to 30 million IREN shares at $70 each”.

Related: NVIDIA and IREN (2026-05-07).

NVIDIAup to $2.1B5 GWAnnounced
Anthropic
Details for Anthropic and SpaceX, 2026-05-06

Anthropic signed an agreement to use all of the compute capacity at SpaceX's Colossus 1 data center, more than 300 MW and over 220,000 NVIDIA GPUs. SpaceX's IPO filings said its Cloud Services Agreements with Anthropic cover about 325,000 NVIDIA GPUs across Colossus and Colossus II at $1.25 billion per month through May 2029, terminable on 90 days' notice after an initial three months.

With xAI. Chips: NVIDIA H100, NVIDIA H200, NVIDIA GB200. Starts 2026-05. Stated as “$1.25 billion per month through May 2029”.

  • : SpaceX's S-1 said the agreements cover Colossus and Colossus II at $1.25 billion per month through May 2029, terminable on 90 days' notice. Source

Related: xAI and NVIDIA (2024-10-28); Google and SpaceX (2026-06-05).

SpaceX—325,000 NVIDIA GPUs across Colossus and Colossus II (approximately)Signed
Microsoft
Details for Microsoft and Nscale, 2026-05-05

Nscale said it would deliver more than 66,000 NVIDIA Rubin GPUs to Microsoft at Start Campus's site in Sines, Portugal, investing EUR 230 million in shared infrastructure and EUR 465 million in a second 200 MW building.

Chips: NVIDIA Rubin.

Related: Microsoft and Nscale (2025-10-15); Microsoft and Nscale (2026-04-14).

Nscale—66,000 NVIDIA Rubin GPUsAnnounced
Anthropic
Details for Anthropic and Amazon Web Services, 2026-04-20

Anthropic committed more than $100 billion over ten years to AWS technologies, securing up to 5 GW of new capacity across Graviton and Trainium2 through Trainium4, with nearly 1 GW of Trainium2 and Trainium3 capacity due by the end of 2026. Amazon invested $5 billion in Anthropic with up to $20 billion more possible.

With Amazon. Chips: AWS Trainium2, AWS Trainium3, AWS Trainium4, AWS Graviton. Term: 10 years. Starts 2026. Stated as “more than $100 billion over the next ten years to AWS technologies”.

Related: Anthropic and Amazon Web Services (2023-09-25); Anthropic and Amazon Web Services (2024-11-22); Anthropic and Amazon Web Services (2024-12-03).

Amazon Web Services$100Bcontract value5 GWIn progress
Microsoft
Details for Microsoft and Nscale, 2026-04-14

Nscale expanded its Microsoft agreement to add more than 30,000 NVIDIA Rubin GPUs at its 230 MW Narvik, Norway campus for delivery in 2027, after rolling up the former Aker-Nscale joint venture.

Chips: NVIDIA Vera Rubin. Starts 2027.

Related: Microsoft and Nscale (2025-10-15); OpenAI and Nscale (2025-07-31); Microsoft and Nscale (2026-05-05).

Nscale—30,000 NVIDIA Rubin GPUs (more than)Signed
Anthropic
Details for Anthropic and CoreWeave, 2026-04-10

CoreWeave signed a multi-year agreement to run Anthropic's Claude workloads at production scale on its cloud, starting with a phased rollout that could expand over time. Financial terms were not disclosed.

Starts 2026.

Related: Meta and CoreWeave (2026-04-09).

CoreWeave——Signed
Meta
Details for Meta and CoreWeave, 2026-04-09

CoreWeave and Meta signed an expanded agreement for AI cloud capacity through December 2032 worth about $21 billion, including some of the first NVIDIA Vera Rubin deployments. The total includes Meta exercising an option under its September 2025 order form.

Chips: NVIDIA Vera Rubin. Stated as “approximately $21 billion”.

Related: Meta and CoreWeave (2025-09-30).

CoreWeave$21Bcontract value—Signed
Anthropic
Details for Anthropic and Google, 2026-04-06

Anthropic signed an agreement with Google and Broadcom for multiple gigawatts of next-generation TPU capacity coming online from 2027, mostly in the US, and later described it as a 5 GW agreement. The Information reported in May 2026 that Anthropic committed to spend about $200 billion with Google Cloud over five years; neither company confirmed that figure.

With Broadcom. Chips: Google TPU. Term: 5 years. Starts 2027. Stated as “US$200 billion (HK$1.56 trillion) with Google Cloud over five years”.

  • : The Information reported a roughly $200 billion five-year Google Cloud commitment by Anthropic and that Alphabet is investing up to $40 billion in Anthropic. Source

Related: Anthropic and Google Cloud (2025-10-23); Anthropic and Broadcom (2025-12-11); Anthropic and Fluidstack (2025-11-12).

Google$200Bpress-reported5 GWSigned
Meta
Details for Meta and Nebius, 2026-03-16

Nebius signed a five-year agreement to provide Meta $12 billion of dedicated capacity on NVIDIA Vera Rubin systems from early 2027, and Meta committed to buy up to $15 billion of additional capacity on upcoming Nebius clusters, for a total contract value of up to about $27 billion.

Chips: NVIDIA Vera Rubin. Term: 5 years. Starts 2027. Stated as “a contract value of up to approximately $27 billion”.

Related: Meta and Nebius (2025-11-11); Nebius and NVIDIA (2026-03-11).

Nebiusup to $27B—Signed
Nebius
Details for Nebius and NVIDIA, 2026-03-11

NVIDIA agreed to invest $2 billion in Nebius as part of a strategic partnership to help Nebius deploy more than 5 GW of capacity by the end of 2030 on NVIDIA's latest platforms.

Stated as “NVIDIA will invest $2 billion in Nebius”.

Related: Meta and Nebius (2026-03-16); CoreWeave and NVIDIA (2026-01-26).

NVIDIA$2Binvestment5 GWAnnounced
Thinking Machines Lab
Details for Thinking Machines Lab and NVIDIA, 2026-03-10

Thinking Machines Lab said it struck a multi-year partnership with NVIDIA to procure at least 1 GW of Vera Rubin systems from early 2027, mainly for training, alongside a significant NVIDIA investment. Financial terms were not disclosed.

Chips: NVIDIA Vera Rubin. Starts 2027.

NVIDIA—1 GWSigned
OpenAI
Details for OpenAI and Amazon Web Services, 2026-02-27

OpenAI and AWS expanded their $38 billion agreement by $100 billion over eight years, with OpenAI committing to consume about 2 GW of Trainium3 and Trainium4 capacity. Amazon also agreed to invest $50 billion in OpenAI, starting with $15 billion and adding $35 billion when certain conditions are met.

With Amazon. Chips: AWS Trainium3, AWS Trainium4. Term: 8 years. Stated as “expanding their existing $38 billion multi-year agreement by $100 billion over 8 years”.

Related: OpenAI and Amazon Web Services (2025-11-03).

Amazon Web Services$100Bcontract value2 GWSigned
Meta
Details for Meta and Google Cloud, 2026-02-26

The Information reported that Meta agreed to a multibillion-dollar deal to rent Google Cloud TPUs for developing its AI models. Neither company announced terms.

Chips: Google TPU. Stated as “multibillion-dollar deal”.

Related: Meta and Google Cloud (2025-08-21).

Google Cloud——Reported
Meta
Details for Meta and AMD, 2026-02-24

AMD and Meta signed a definitive multi-year agreement for Meta to deploy up to 6 GW of AMD Instinct GPUs, starting with shipments of a custom MI450-based GPU in Helios racks in the second half of 2026. AMD issued Meta a warrant for up to 160 million AMD shares that vests as shipments scale; no dollar value was disclosed.

Chips: AMD MI450. Starts 2026. Stated as “performance-based warrant for up to 160 million shares of AMD common stock”.

Related: Meta and NVIDIA (2026-02-17); OpenAI and AMD (2025-10-06).

AMD—6 GWSigned
OpenAI
Details for OpenAI and Tata Consultancy Services (HyperVault), 2026-02-19

OpenAI said it will become the first customer of TCS's HyperVault data center business in India under its Stargate initiative, starting with 100 MW of capacity with potential to scale to 1 GW over time. No financial terms were disclosed.

With Tata Group.

Related: OpenAI and Stargate Project (2025-01-21).

Tata Consultancy Services (HyperVault)—100 MWAnnounced
Meta
Details for Meta and NVIDIA, 2026-02-17

NVIDIA and Meta announced a multiyear, multigenerational partnership covering millions of NVIDIA Blackwell and Rubin GPUs, standalone Grace CPUs and Spectrum-X Ethernet switches across Meta's own data centers and NVIDIA cloud partners. No financial terms were disclosed.

Chips: NVIDIA Blackwell, NVIDIA Rubin, NVIDIA Grace.

Related: Meta and AMD (2026-02-24).

NVIDIA——Signed
CoreWeave
Details for CoreWeave and NVIDIA, 2026-01-26

NVIDIA bought $2 billion of CoreWeave stock at $87.20 per share and the two companies expanded their collaboration to help CoreWeave build more than 5 GW of AI factories by 2030 on NVIDIA platforms.

Stated as “NVIDIA has invested $2 billion in CoreWeave Class A common stock”.

Related: NVIDIA and CoreWeave (2025-09-15).

NVIDIA$2Binvestment5 GWSigned
OpenAI
Details for OpenAI and Cerebras, 2026-01-14

OpenAI agreed to buy up to 750 MW of low-latency inference compute from Cerebras over three years, delivered from Cerebras-built or leased data centers in tranches through 2028. Reuters first reported the deal at more than $10 billion; Cerebras's IPO prospectus of May 2026 values it at more than $20 billion.

Term: 3 years. Stated as “more than $20 billion”.

Cerebras$20Bcontract value750 MWSigned
Meta
Details for Meta and Vistra, 2026-01-09

Meta announced nuclear agreements with Vistra, TerraPower and Oklo supporting up to 6.6 GW of new and existing capacity by 2035, including 20-year Vistra PPAs for 2,176 MW, funding for up to eight TerraPower Natrium reactors and a 1.2 GW Oklo campus in Pike County, Ohio. The power supports grids serving Meta's Prometheus cluster in Ohio.

With TerraPower, Oklo.

Vistra—6.6 GWSigned
OpenAI
Details for OpenAI and SB Energy, 2026-01-09

OpenAI and SoftBank Group each invested $500 million in SB Energy, and OpenAI signed a 1.2 GW data center lease with SB Energy, which will build and operate OpenAI's Stargate site in Milam County, Texas.

With SoftBank Group. Stated as “OpenAI and SoftBank Group are each investing $500 million into SB Energy”.

Related: OpenAI and Oracle (2025-09-23); OpenAI and Stargate Project (2025-01-21).

SB Energy$1Binvestment1.2 GWSigned
xAI
Details for xAI and Series E investors, 2026-01-06

xAI closed an upsized $20 billion Series E with NVIDIA and Cisco Investments as strategic investors backing its compute buildout, saying Colossus I and II ended 2025 with over one million H100 GPU equivalents. The equity and debt split was not disclosed by xAI.

With NVIDIA, Cisco Investments. Stated as “raised $20 billion”.

Related: xAI and NVIDIA (2025-10); xAI and Morgan Stanley (arranger) (2025-06-30).

Series E investors$20Binvestment—Signed
Anthropic
Details for Anthropic and Hut 8, 2025-12-17

Hut 8 agreed to develop at least 245 MW and up to 2,295 MW of AI data center capacity for Anthropic, starting with a 15-year, $7.0 billion lease to Fluidstack for 245 MW at River Bend, Louisiana, backstopped by Google. Anthropic said the capacity is an expansion of its work with Fluidstack and should come online by early 2027.

With Fluidstack, Google. Term: 15 years. Starts 2027. Stated as “a 15-year, $7.0 billion lease”.

Related: Anthropic and Fluidstack (2025-11-12); Fluidstack and TeraWulf (2025-08-14).

Hut 8$7Bcontract value245 MWSigned
Anthropic
Details for Anthropic and Broadcom, 2025-12-11

Broadcom said on its December 2025 earnings call that Anthropic was the customer behind a $10 billion order for Google TPU Ironwood racks disclosed in September 2025, and that Anthropic placed a further $11 billion order for delivery in late 2026. Press reports in September 2025 had attributed the $10 billion order to OpenAI.

With Google. Chips: Google TPU Ironwood. Starts 2026. Stated as “a $10 billion order to sell the latest TPU ironwood racks to Anthropic; an additional $11 billion order from this same customer”.

Related: Anthropic and Google Cloud (2025-10-23); Anthropic and Google (2026-04-06); Anthropic and Broadcom (2026-10-01).

Broadcom$21Bcontract value—Signed
HUMAIN
Details for HUMAIN and NVIDIA, 2025-11-19

HUMAIN expanded its NVIDIA partnership with plans to deploy up to 600,000 NVIDIA GPUs, including GB300 systems, in Saudi Arabia and the US over three years. The same announcement covered a 500 MW xAI data center and an AWS AI Zone in Riyadh with up to 150,000 NVIDIA GPUs.

With Global AI, xAI, Amazon Web Services. Chips: NVIDIA GB300. Term: 3 years.

Related: HUMAIN and NVIDIA (2025-05-13); xAI and HUMAIN (2025-11-19).

NVIDIA—600,000 NVIDIA GPUs (up to)Announced
xAI
Details for xAI and HUMAIN, 2025-11-19

HUMAIN and xAI agreed to jointly develop a network of data centers in Saudi Arabia anchored by a flagship facility of 500 MW or more, xAI's first large deployment outside the US.

With NVIDIA. Chips: NVIDIA GB300.

Related: HUMAIN and NVIDIA (2025-11-19); HUMAIN and NVIDIA (2025-05-13).

HUMAIN—500 MWAnnounced
Anthropic
Details for Anthropic and Microsoft, 2025-11-18

Anthropic committed to buy $30 billion of Azure compute capacity and to contract up to 1 GW of additional capacity on NVIDIA Grace Blackwell and Vera Rubin systems. NVIDIA and Microsoft committed to invest up to $10 billion and up to $5 billion in Anthropic.

With NVIDIA. Chips: NVIDIA Grace Blackwell, NVIDIA Vera Rubin. Stated as “$30 billion of Azure compute capacity”.

Related: Anthropic and Google Cloud (2025-10-23); Anthropic and Fluidstack (2025-11-12).

Microsoft$30Bcontract value1 GWSigned
Anthropic
Details for Anthropic and Fluidstack, 2025-11-12

Anthropic announced a $50 billion investment in US computing infrastructure, building custom data centers with Fluidstack in Texas and New York, with sites coming online through 2026 and more sites to come.

Starts 2026. Stated as “a $50 billion investment in American computing infrastructure”.

  • : Anthropic said the Google and Broadcom TPU deal, mostly sited in the US, is a major expansion of this $50 billion commitment. Source

Related: Anthropic and Google (2026-04-06); Anthropic and Hut 8 (2025-12-17); Anthropic and TeraWulf (2026-07-06); Anthropic and AMD (2026-07-22).

Fluidstack$50Binvestment—In progress
Meta
Details for Meta and Nebius, 2025-11-11

Nebius disclosed with its third-quarter 2025 results a new agreement to deliver AI infrastructure to Meta valued at about $3 billion over five years.

Term: 5 years. Stated as “approximately $3 billion over 5 years”.

Related: Meta and Nebius (2026-03-16).

Nebius$3Bcontract value—Signed
Amazon Web Services
Details for Amazon Web Services and Cipher Mining, 2025-11-03

Cipher signed a 15-year lease with Amazon Web Services to provide 300 MW of gross capacity for AI workloads, delivered in two phases in 2026, with an estimated contract value of about $5.5 billion.

Term: 15 years. Starts 2026-08. Stated as “~$5.5Bn Estimated Contract Value”.

Related: Fluidstack and Cipher Mining (2025-09-25).

Cipher Mining$5.5Bcontract value300 MWSigned
Microsoft
Details for Microsoft and IREN, 2025-11-03

IREN agreed to give Microsoft access to NVIDIA GB300 GPUs over five years for about $9.7 billion including a 20% prepayment, deployed in phases through 2026 at its Childress, Texas campus in new data centers supporting 200 MW of IT load. IREN agreed to buy the GPUs and equipment from Dell for about $5.8 billion.

With Dell Technologies. Chips: NVIDIA GB300. Term: 5 years. Stated as “a total contract value of approximately $9.7 billion, including a 20% prepayment”.

Related: Microsoft and Nebius (2025-09-08); Microsoft and Nscale (2025-10-15); Microsoft and Lambda (2025-11-03).

IREN$9.7Bcontract value200 MWIn progress
Microsoft
Details for Microsoft and Lambda, 2025-11-03

Lambda signed a multibillion-dollar, multi-year agreement to deploy AI infrastructure for Microsoft powered by tens of thousands of NVIDIA GPUs, including GB300 NVL72 systems. The exact value and GPU count were not disclosed.

Chips: NVIDIA GB300. Stated as “multibillion-dollar agreement”.

Related: Microsoft and Nebius (2025-09-08); Microsoft and Nscale (2025-10-15); Microsoft and IREN (2025-11-03); NVIDIA and Lambda (2025-09).

Lambda——Signed
OpenAI
Details for OpenAI and Amazon Web Services, 2025-11-03

AWS and OpenAI signed a $38 billion multi-year agreement giving OpenAI access to hundreds of thousands of NVIDIA GB200 and GB300 GPUs on Amazon EC2 UltraServers, with all capacity targeted for deployment before the end of 2026. The agreement was expanded by $100 billion in February 2026.

Chips: NVIDIA GB200, NVIDIA GB300. Term: 7 years. Starts 2025-11. Stated as “$38 billion agreement, which will have continued growth over the next seven years”.

Related: OpenAI and Amazon Web Services (2026-02-27).

Amazon Web Services$38Bcontract value—In progress
OpenAI
Details for OpenAI and Oracle, 2025-10-30

OpenAI, Oracle and Related Digital announced a Stargate campus of more than a gigawatt in Saline Township, Michigan, developed exclusively for Oracle, with construction expected to begin in early 2026. The site is part of the 4.5 GW Oracle partnership.

With Related Digital. Stated as “multi-billion dollar investment”.

Related: OpenAI and Oracle (2025-07-22).

Oracle——Announced
OpenAI
Details for OpenAI and Microsoft, 2025-10-28

Under a restructured partnership, OpenAI contracted to purchase an incremental $250 billion of Azure services, and Microsoft gave up its right of first refusal to be OpenAI's compute provider. No term length for the commitment was stated.

Stated as “an incremental $250B of Azure services”.

Related: OpenAI and Microsoft (2023-01-23); OpenAI and Microsoft (2025-01-21).

Microsoft$250Bcontract value—Signed
Google
Details for Google and NextEra Energy, 2025-10-27

NextEra Energy agreed with Google to restart the Duane Arnold nuclear plant in Iowa, with Google buying 615 MW of its output for 25 years from the restart, expected in the first quarter of 2029.

Term: 25 years. Starts 2029.

NextEra Energy—615 MWSigned
Anthropic
Details for Anthropic and Google Cloud, 2025-10-23

Anthropic said it would expand its use of Google Cloud to up to one million TPUs, an expansion worth tens of billions of dollars that is expected to bring well over a gigawatt of capacity online in 2026.

Chips: Google TPU. Starts 2026. Stated as “worth tens of billions of dollars”.

Related: Anthropic and Google (2026-04-06); Anthropic and Broadcom (2025-12-11).

Google Cloud—1,000,000 Google TPUs (up to)In progress
OpenAI
Details for OpenAI and Oracle, 2025-10-22

OpenAI, Oracle and Vantage Data Centers announced a Stargate campus in Port Washington, Wisconsin, with four data centers providing close to a gigawatt of AI capacity and completion scheduled for 2028. The site is part of the 4.5 GW Oracle partnership.

With Vantage Data Centers. Stated as “Vantage's $15B+ investment in Port Washington”.

Related: OpenAI and Oracle (2025-07-22); OpenAI and Oracle (2025-09-23).

Oracle$15Binvestment—Announced
Meta
Details for Meta and Blue Owl Capital, 2025-10-21

Meta and funds managed by Blue Owl formed a joint venture, 80% Blue Owl and 20% Meta, to develop and own the Hyperion data center campus in Richland Parish, Louisiana, with about $27 billion in total development costs, partly funded by debt sold to PIMCO and other bond investors. Meta leases the campus on four-year initial terms with extension options and a 16-year residual value guarantee.

With PIMCO. Term: 4 years. Stated as “approximately $27 billion in total development costs”.

  • : Meta said it is expanding the Richland Parish, Louisiana data center to 5 GW of compute capacity. Source

Related: Meta and BlackRock (2026-07-28).

Blue Owl Capital$27Binvestment—In progress
Microsoft
Details for Microsoft and Nscale, 2025-10-15

Nscale signed an expanded deal to provide Microsoft with about 200,000 NVIDIA GB300 GPUs across Texas, Portugal, the UK and Norway, including about 104,000 GPUs at a roughly 240 MW Texas campus from Q3 2026. No contract value was disclosed.

With Dell Technologies, Aker. Chips: NVIDIA GB300. Starts 2026.

Related: Microsoft and Nscale (2026-04-14); OpenAI and Nscale (2025-07-31); Microsoft and Nebius (2025-09-08); Microsoft and IREN (2025-11-03); Microsoft and Lambda (2025-11-03); Microsoft and Nscale (2026-05-05).

Nscale—200,000 NVIDIA GB300 GPUs (approximately)In progress
OpenAI
Details for OpenAI and Broadcom, 2025-10-13

OpenAI and Broadcom signed a term sheet to deploy 10 GW of OpenAI-designed AI accelerators with Broadcom networking, in racks targeted to start deploying in the second half of 2026 and finish by the end of 2029. No dollar value was disclosed.

Chips: OpenAI-designed custom accelerator. Starts 2026.

Related: OpenAI and NVIDIA (2025-09-22); OpenAI and AMD (2025-10-06).

Broadcom—10 GWAnnounced
OpenAI
Details for OpenAI and Sur Energy, 2025-10-10

Sur Energy and OpenAI signed a letter of intent for Stargate Argentina, a data center project of up to 500 MW involving up to $25 billion of investment at full scale under Argentina's RIGI investment regime. In May 2026 the Buenos Aires Times reported the project had not yet been presented to the government.

Stated as “up to $25 billion in investment at full scale”.

  • : Buenos Aires Times reported that more than six months on, the project had not been presented to the government. Source

Related: OpenAI and Stargate Project (2025-01-21).

Sur Energyup to $25B500 MWAnnounced
OpenAI
Details for OpenAI and AMD, 2025-10-06

AMD and OpenAI signed a definitive agreement for OpenAI to deploy 6 GW of AMD Instinct GPUs over multiple generations, starting with 1 GW of MI450 GPUs in the second half of 2026. AMD issued OpenAI a warrant for up to 160 million AMD shares that vests as deployment milestones are met; AMD's CFO said the partnership is expected to deliver tens of billions of dollars in revenue.

Chips: AMD MI450. Starts 2026. Stated as “warrant for up to 160 million shares of AMD common stock”.

Related: OpenAI and NVIDIA (2025-09-22); OpenAI and Broadcom (2025-10-13).

AMD—6 GWSigned
OpenAI
Details for OpenAI and Samsung Electronics, 2025-10-01

OpenAI signed letters of intent with Samsung and SK in Seoul under which Samsung Electronics and SK hynix will supply memory for Stargate; Samsung said OpenAI's memory demand is projected to reach up to 900,000 DRAM wafers per month. The letters also cover data center work in South Korea.

With SK hynix, Samsung SDS, Samsung C&T, Samsung Heavy Industries. Chips: DRAM (HBM) memory.

Related: OpenAI and Stargate Project (2025-01-21).

Samsung Electronics—900,000 DRAM wafers per month (OpenAI's projected memory demand)Announced
xAI
Details for xAI and NVIDIA, 2025-10

Bloomberg reported that xAI was raising about $20 billion through a special-purpose vehicle that would buy NVIDIA chips and lease them to xAI for five years for its Colossus 2 data center, with NVIDIA investing about $2 billion of the equity. The companies did not confirm the structure.

With Apollo Global Management, Diameter Capital Partners, Valor Capital. Term: 5 years. Stated as “about $7.5 billion in equity and up to $12.5 billion in debt”.

Related: xAI and Morgan Stanley (arranger) (2025-06-30); xAI and Series E investors (2026-01-06).

NVIDIA$20Bpress-reported—Reported
Meta
Details for Meta and CoreWeave, 2025-09-30

Meta committed to pay CoreWeave up to about $14.2 billion for cloud capacity through December 14, 2031, with an option to expand through 2032. Meta exercised that option as part of a roughly $21 billion expanded agreement in April 2026.

Stated as “up to approximately $14.2 billion through December 14, 2031”.

  • : CoreWeave announced an expanded agreement with Meta worth about $21 billion through December 2032, including exercise of the earlier option. Source

Related: Meta and CoreWeave (2026-04-09).

CoreWeaveup to $14.2B—Amended
Fluidstack
Details for Fluidstack and Cipher Mining, 2025-09-25

Cipher signed a 10-year agreement to host 168 MW of critical IT load for Fluidstack at Barber Lake, Texas, worth about $3 billion, with Google backstopping $1.4 billion of Fluidstack's obligations for about a 5.4% stake in Cipher. In September 2026 the lease was extended to 20 years after an unnamed leading AI lab committed to a follow-on term.

With Google. Term: 10 years. Stated as “~$3 Billion in Contracted Revenue over 10-Year Term”.

  • : Cipher signed an additional 56 MW, 10-year hosting agreement with Fluidstack. Source
  • : Barber Lake lease term extended to 20 years, raising contracted revenue to over $9 billion, with a leading AI lab committed to the added 10-year term. Source

Related: Fluidstack and TeraWulf (2025-08-14); Amazon Web Services and Cipher Mining (2025-11-03).

Cipher Mining$3Bcontract value168 MWIn progress
OpenAI
Details for OpenAI and CoreWeave, 2025-09-25

CoreWeave and OpenAI signed a new order form under which OpenAI committed to pay up to about $6.5 billion through May 31, 2031 for reserved cloud capacity. CoreWeave said this brought its total contract value with OpenAI to about $22.4 billion.

Stated as “up to approximately $6.5 billion through May 31, 2031”.

Related: OpenAI and CoreWeave (2025-03-10).

CoreWeaveup to $6.5B—Signed
OpenAI
Details for OpenAI and Oracle, 2025-09-23

OpenAI, Oracle and SoftBank named five new US Stargate sites: Shackelford County, Texas, Dona Ana County, New Mexico and a Midwest site with Oracle, able to deliver over 5.5 GW together with a 600 MW Abilene expansion, plus SoftBank sites in Lordstown, Ohio and Milam County, Texas that can scale to 1.5 GW. The partners said this brought Stargate to nearly 7 GW of planned capacity and over $400 billion of investment over three years.

With SoftBank, SB Energy.

  • : The Midwest site was named as Port Washington, Wisconsin, developed with Vantage Data Centers. Source
  • : SB Energy was selected to build and operate the 1.2 GW Milam County site under a lease with OpenAI. Source

Related: OpenAI and Stargate Project (2025-01-21); OpenAI and Oracle (2025-07-22); OpenAI and Oracle (2025-10-22); OpenAI and SB Energy (2026-01-09).

Oracle——In progress
OpenAI
Details for OpenAI and NVIDIA, 2025-09-22

OpenAI and NVIDIA signed a letter of intent for OpenAI to deploy at least 10 GW of NVIDIA systems, with NVIDIA intending to invest up to $100 billion in OpenAI as each gigawatt is deployed. The first gigawatt was targeted for the second half of 2026 on the Vera Rubin platform.

Chips: NVIDIA Vera Rubin. Starts 2026. Stated as “NVIDIA intends to invest up to $100 billion in OpenAI progressively as each gigawatt is deployed”.

  • : NVIDIA's annual report said it was still finalizing an investment and partnership agreement with OpenAI, with no assurance a transaction would be completed. Source
  • : OpenAI said NVIDIA would invest $30 billion in its $110 billion funding round; Reuters said it was unclear whether this replaced the up to $100 billion commitment. Source
  • : NVIDIA agreed to guarantee up to $105 billion of lease obligations for an Ohio campus where OpenAI will deploy NVIDIA systems on about 4.25 GW of IT load. Source

Related: OpenAI and AMD (2025-10-06); OpenAI and Broadcom (2025-10-13); OpenAI and SB Energy (2026-08-17).

NVIDIAup to $100B10 GWAnnounced
OpenAI
Details for OpenAI and Nscale, 2025-09-16

OpenAI announced Stargate UK with NVIDIA and Nscale, saying it will explore offtake of up to 8,000 GPUs in the first quarter of 2026 with potential to scale to 31,000 GPUs, across UK sites including Cobalt Park in the North East.

With NVIDIA. Starts 2026.

Related: OpenAI and Nscale (2025-07-31); Microsoft and Nscale (2025-10-15).

Nscale—8,000 GPUs (offtake to explore in Q1 2026; up to 31,000 over time)Announced
NVIDIA
Details for NVIDIA and CoreWeave, 2025-09-15

CoreWeave disclosed a $6.3 billion order form with NVIDIA under which NVIDIA must buy any residual cloud capacity that CoreWeave's own customers do not use, through April 13, 2032.

Stated as “an initial value of $6.3 billion”.

Related: CoreWeave and NVIDIA (2026-01-26); NVIDIA and Lambda (2025-09).

CoreWeave$6.3Bcontract value—Signed
OpenAI
Details for OpenAI and Oracle, 2025-09-10

The Wall Street Journal reported, citing people familiar with the agreement, that OpenAI signed a contract to buy about $300 billion of Oracle computing power over roughly five years starting in 2027, about seven weeks after the 4.5 GW Oracle partnership was announced. On September 23, 2025 OpenAI put that partnership at more than $300 billion over five years. Oracle has not stated the figure, and neither company has confirmed the 2027 start.

Term: 5 years. Starts 2027. Stated as “more than $300 billion over five years”.

Related: OpenAI and Oracle (2025-07-22); OpenAI and Oracle (2024-06-11).

Oracle$300Bcontract value—Signed
Microsoft
Details for Microsoft and Nebius, 2025-09-08

Nebius agreed to provide Microsoft dedicated GPU capacity from its new Vineland, New Jersey data center over five years, for a contract value of about $17.4 billion through 2031, or about $19.4 billion if Microsoft takes additional services. Capacity was to be deployed in tranches in 2025 and 2026.

Term: 5 years. Starts 2025. Stated as “about $17.4 billion through 2031”.

Related: Microsoft and Nscale (2025-10-15); Microsoft and IREN (2025-11-03); Microsoft and Lambda (2025-11-03).

Nebius$17.4Bcontract value—In progress
NVIDIA
Details for NVIDIA and Lambda, 2025-09

The Information reported that NVIDIA agreed to lease back about 18,000 of its own GPUs from Lambda, a company it had invested in, for about $1.5 billion: roughly $1.3 billion over four years for 10,000 GPUs plus about $200 million for 8,000 more. Neither company disclosed terms.

Term: 4 years. Stated as “$1.5 billion”.

Related: Lambda and Macquarie Group (2024-04-04); Microsoft and Lambda (2025-11-03); NVIDIA and CoreWeave (2025-09-15).

Lambda$1.5Bpress-reported18,000 GPUs (reported)Reported
CoreWeave
Details for CoreWeave and Applied Digital, 2025-08-29

Applied Digital signed a third lease with CoreWeave for 150 MW at its Polaris Forge 1 campus in Ellendale, North Dakota, bringing CoreWeave's leases there to 400 MW and about $11 billion of anticipated lease revenue, including $7 billion from two roughly 15-year leases executed in May 2025.

Term: 15 years. Stated as “total anticipated contracted lease revenue to approximately $11B”.

Related: NVIDIA and CoreWeave (2025-09-15).

Applied Digital$11Bcontract value400 MWIn progress
Meta
Details for Meta and Google Cloud, 2025-08-21

Reuters reported, citing a source, that Google signed a six-year cloud deal with Meta worth more than $10 billion for servers, storage and networking. The deal was first reported by The Information; neither company disclosed terms.

Term: 6 years. Stated as “worth more than $10 billion”.

Google Cloud$10Bpress-reported—Reported
Fluidstack
Details for Fluidstack and TeraWulf, 2025-08-14

TeraWulf signed two 10-year colocation agreements with Fluidstack for more than 200 MW of critical IT load at Lake Mariner, New York, worth about $3.7 billion and up to $8.7 billion with extensions. Google backstopped $1.8 billion of Fluidstack's obligations and received warrants for about an 8% stake in TeraWulf.

With Google. Term: 10 years. Stated as “approximately $3.7 billion in contracted revenue”.

  • : TeraWulf announced a Fluidstack expansion with a 160 MW CB-5 lease at Lake Mariner. Source

Related: Fluidstack and Cipher Mining (2025-09-25); Anthropic and Hut 8 (2025-12-17).

TeraWulf$3.7Bcontract value200 MWIn progress
CoreWeave
Details for CoreWeave and Morgan Stanley and MUFG (lead arrangers), 2025-07-31

CoreWeave closed a $2.6 billion secured delayed draw term loan (DDTL 3.0) led by Morgan Stanley and MUFG to buy equipment and infrastructure for its long-term contract with OpenAI.

With Goldman Sachs, OpenAI. Stated as “$2.6 billion delayed draw term loan facility”.

Related: OpenAI and CoreWeave (2025-03-10).

Morgan Stanley and MUFG (lead arrangers)$2.6Bcontract value—Signed
OpenAI
Details for OpenAI and Nscale, 2025-07-31

Nscale, Aker and OpenAI announced Stargate Norway in Narvik, planned at 230 MW with an ambition for 290 MW more and a target of 100,000 NVIDIA GPUs by the end of 2026, with OpenAI as an initial offtaker. Nscale and Aker committed about $1 billion to the first 20 MW phase; the Aker-Nscale venture later contracted Narvik capacity to Microsoft.

With Aker. Stated as “approximately USD 1 billion to the initial 20MW phase of the project”.

  • : Nscale said the Aker-Nscale joint venture had signed a multi-year agreement to deliver about 52,000 NVIDIA GB300 GPUs to Microsoft from Narvik. Source

Related: Microsoft and Nscale (2025-10-15); Microsoft and Nscale (2026-04-14); OpenAI and Stargate Project (2025-01-21).

Nscale$1Binvestment230 MWAnnounced
OpenAI
Details for OpenAI and Oracle, 2025-07-22

Oracle and OpenAI agreed to develop 4.5 GW of additional Stargate data center capacity in the US, which OpenAI said would bring Stargate capacity under development to over 5 GW including Abilene. On June 30, 2025 Oracle had disclosed an unnamed cloud contract expected to contribute more than $30 billion in annual revenue starting in fiscal 2028.

  • : OpenAI put the 4.5 GW partnership at more than $300 billion between the two companies over five years. Source
  • : Port Washington, Wisconsin campus with Vantage named as part of the 4.5 GW partnership. Source
  • : Saline Township, Michigan campus with Related Digital named as part of the 4.5 GW partnership. Source

Related: OpenAI and Oracle (2025-09-10); OpenAI and Oracle (2024-06-11); OpenAI and Stargate Project (2025-01-21); OpenAI and Oracle (2025-09-23); OpenAI and Oracle (2025-10-22); OpenAI and Oracle (2025-10-30); Crusoe and Blue Owl Capital (2025-05-21).

Oracle—4.5 GWIn progress
xAI
Details for xAI and Morgan Stanley (arranger), 2025-06-30

Morgan Stanley said xAI raised $5 billion of secured notes and term loans plus $5 billion of strategic equity, with proceeds going to AI infrastructure including one of the world's largest data centers. The figures come from the arranging bank as reported by press, not from xAI.

Stated as “$10 billion in debt and equity”.

Related: xAI and NVIDIA (2025-10); xAI and Series E investors (2026-01-06).

Morgan Stanley (arranger)$10Bpress-reported—Signed
Amazon Web Services
Details for Amazon Web Services and Talen Energy, 2025-06-11

Talen Energy expanded its nuclear power agreement with Amazon to up to 1,920 MW from the Susquehanna plant in Pennsylvania through 2042, reaching the full volume no later than 2032.

Talen Energy—1.92 GWSigned
OpenAI
Details for OpenAI and Google Cloud, 2025-06-10

Reuters reported, citing three sources, that OpenAI would add Google Cloud capacity for training and running its models in a deal finalized in May 2025. Neither company disclosed terms.

Related: OpenAI and Google Cloud (2025-06).

Google Cloud——Reported
Meta
Details for Meta and Constellation Energy, 2025-06-03

Meta signed a 20-year agreement for the output of Constellation's Clinton nuclear plant in Illinois, 1,121 MW including a 30 MW uprate, starting in June 2027.

Term: 20 years. Starts 2027-06.

Constellation Energy—1.12 GWSigned
OpenAI
Details for OpenAI and Google Cloud, 2025-06

Reuters and other outlets reported in late June 2025 that OpenAI had begun renting Google TPUs. OpenAI then said it was only in early testing with some TPUs and had no active plans to deploy them at scale.

Chips: Google TPU.

Related: OpenAI and Google Cloud (2025-06-10).

Google Cloud——Reported, denied
OpenAI
Details for OpenAI and G42, 2025-05-22

OpenAI announced Stargate UAE with G42, Oracle, NVIDIA, Cisco and SoftBank: a 1 GW cluster in Abu Dhabi, with the first 200 MW expected to go live in 2026. In October 2025 G42 said construction of the first 200 MW was well underway.

With Oracle, NVIDIA, Cisco, SoftBank. Starts 2026.

  • : G42 said construction of the first 200 MW was well underway toward planned 2026 delivery. Source

Related: OpenAI and Stargate Project (2025-01-21).

G42—1 GWIn progress
Crusoe
Details for Crusoe and Blue Owl Capital, 2025-05-21

Crusoe, Blue Owl and Primary Digital Infrastructure began the second phase of a $15 billion joint venture to fund the 1.2 GW Abilene, Texas campus, adding six buildings for eight in total. The campus runs on Oracle Cloud Infrastructure as Stargate's flagship site for OpenAI, with the first NVIDIA GB200 racks delivered in June 2025.

With Primary Digital Infrastructure, Oracle, OpenAI. Chips: NVIDIA GB200. Stated as “a $15 billion joint-venture”.

  • : Crusoe said the first phase of the Abilene campus was live on Oracle Cloud Infrastructure. Source
  • : Oracle said 6 of the 8 Abilene buildings, 618 MW and 75% of capacity, had been delivered to the customer. Source

Related: OpenAI and Stargate Project (2025-01-21); OpenAI and Oracle (2025-07-22).

Blue Owl Capital$15Binvestment1.2 GWIn progress
HUMAIN
Details for HUMAIN and NVIDIA, 2025-05-13

Saudi Arabia's HUMAIN and NVIDIA announced plans for AI factories of up to 500 MW powered by several hundred thousand NVIDIA GPUs over five years, starting with an 18,000-GPU GB300 supercomputer. The partnership was expanded in November 2025.

Chips: NVIDIA GB300. Term: 5 years.

Related: HUMAIN and NVIDIA (2025-11-19); xAI and HUMAIN (2025-11-19).

NVIDIA—500 MWIn progress
HUMAIN
Details for HUMAIN and AMD, 2025-05-13

AMD and Saudi Arabia's HUMAIN announced a $10 billion collaboration to deploy 500 MW of AI compute built on AMD hardware.

Stated as “a $10 billion collaboration”.

AMD$10Binvestment500 MWAnnounced
OpenAI
Details for OpenAI and CoreWeave, 2025-03-10

CoreWeave agreed to supply AI cloud capacity to OpenAI under a contract worth up to $11.9 billion through October 2030, and OpenAI received $350 million of CoreWeave stock as part of the deal. CoreWeave later financed equipment for the contract with a $2.6 billion delayed draw term loan.

Stated as “up to $11.9 billion”.

  • : CoreWeave later said the contract was expanded by up to $4 billion in May 2025. Source
  • : OpenAI committed up to about $6.5 billion more through May 31, 2031 under a new order form. Source

Related: OpenAI and CoreWeave (2025-09-25); CoreWeave and Morgan Stanley and MUFG (lead arrangers) (2025-07-31).

CoreWeaveup to $11.9B—In progress
OpenAI
Details for OpenAI and Microsoft, 2025-01-21

Microsoft and OpenAI replaced Azure exclusivity on new OpenAI capacity with a Microsoft right of first refusal, and Microsoft approved OpenAI building additional capacity, primarily for research and training. The change was announced alongside the Stargate Project.

  • : The right of first refusal on OpenAI compute ended under the restructured agreement. Source

Related: OpenAI and Microsoft (2023-01-23); OpenAI and Microsoft (2025-10-28); OpenAI and Stargate Project (2025-01-21).

Microsoft——Amended
OpenAI
Details for OpenAI and Stargate Project, 2025-01-21

OpenAI, SoftBank, Oracle and MGX launched the Stargate Project, a new company that intends to invest $500 billion over four years in AI infrastructure for OpenAI in the United States, starting with $100 billion. SoftBank has financial responsibility and OpenAI operational responsibility.

With SoftBank, Oracle, MGX, Arm, Microsoft, NVIDIA. Term: 4 years. Starts 2025. Stated as “$500 billion over the next four years”.

  • : Oracle partnership for 4.5 GW of additional US capacity brought Stargate capacity under development to over 5 GW. Source
  • : Five new sites brought Stargate to nearly 7 GW of planned capacity and over $400 billion of investment over three years. Source

Related: OpenAI and Microsoft (2025-01-21); OpenAI and Oracle (2025-07-22); OpenAI and Oracle (2025-09-23); Crusoe and Blue Owl Capital (2025-05-21).

Stargate Project$500Binvestment—In progress
Anthropic
Details for Anthropic and Amazon Web Services, 2024-12-03

AWS announced Project Rainier, an EC2 UltraCluster of Trainium2 UltraServers built with Anthropic and spanning hundreds of thousands of Trainium2 chips. AWS said in October 2025 that it was fully operational with nearly half a million Trainium2 chips.

Chips: AWS Trainium2.

  • : AWS said Project Rainier was fully operational and that Claude would run on more than 1 million Trainium2 chips by the end of 2025. Source

Related: Anthropic and Amazon Web Services (2024-11-22); Anthropic and Amazon Web Services (2026-04-20).

Amazon Web Services——Operating
Anthropic
Details for Anthropic and Amazon Web Services, 2024-11-22

Amazon invested a further $4 billion in Anthropic, bringing its total to $8 billion, and AWS became Anthropic's primary cloud and training partner, with Anthropic working with Annapurna Labs on future Trainium chips.

With Amazon. Chips: AWS Trainium. Stated as “a new $4 billion investment from Amazon”.

Related: Anthropic and Amazon Web Services (2023-09-25); Anthropic and Amazon Web Services (2024-12-03); Anthropic and Amazon Web Services (2026-04-20).

Amazon Web Services$4Binvestment—Signed
xAI
Details for xAI and NVIDIA, 2024-10-28

NVIDIA said xAI's Colossus cluster in Memphis, Tennessee comprised 100,000 NVIDIA Hopper GPUs on Spectrum-X Ethernet, built in 122 days, and that xAI was doubling it to 200,000 Hopper GPUs. Purchase terms were not disclosed; in May 2026 Anthropic contracted all of Colossus 1's capacity.

Chips: NVIDIA H100. Starts 2024.

  • : Anthropic signed an agreement to use all of the compute capacity at Colossus 1, more than 300 MW. Source

Related: Anthropic and SpaceX (2026-05-06); xAI and Morgan Stanley (arranger) (2025-06-30); xAI and NVIDIA (2025-10).

NVIDIA—100,000 NVIDIA Hopper GPUsOperating
Google
Details for Google and Kairos Power, 2024-10-14

Google agreed to buy power from several small modular reactors to be developed by Kairos Power, up to 500 MW in total, with the first reactor targeted for 2030 and the rest through 2035.

Kairos Power—500 MWSigned
Microsoft
Details for Microsoft and Constellation Energy, 2024-09-20

Constellation signed a 20-year power purchase agreement with Microsoft to restart Three Mile Island Unit 1 as the Crane Clean Energy Center, adding about 835 MW of carbon-free power for Microsoft's PJM data centers, expected online in 2028.

Term: 20 years. Starts 2028.

Constellation Energy—835 MWSigned
OpenAI
Details for OpenAI and Oracle, 2024-06-11

Oracle, Microsoft and OpenAI agreed to extend the Microsoft Azure AI platform to Oracle Cloud Infrastructure to give OpenAI additional capacity. No contract value or capacity figure was disclosed.

With Microsoft.

Related: OpenAI and Oracle (2025-07-22); OpenAI and Oracle (2025-09-10).

Oracle——Announced
CoreWeave
Details for CoreWeave and Blackstone, 2024-05-17

CoreWeave signed a $7.5 billion debt facility led by Blackstone, with Magnetar and Coatue, to expand its GPU fleet for existing customer contracts; CoreWeave called it one of the largest private financings in history.

With Magnetar, Coatue, Carlyle, CDPQ, DigitalBridge Credit, BlackRock, Eldridge Industries, Great Elm Capital. Stated as “a $7.5 billion debt financing facility”.

Related: CoreWeave and Magnetar Capital and Blackstone (2023-08-03); CoreWeave and Morgan Stanley and MUFG (lead arrangers) (2025-07-31).

Blackstone$7.5Bcontract value—Signed
Lambda
Details for Lambda and Macquarie Group, 2024-04-04

Lambda secured a GPU-backed special purpose financing vehicle of up to $500 million, led by Macquarie, to expand its on-demand NVIDIA GPU cloud.

With Industrial Development Funding. Stated as “a special purpose GPU financing vehicle of up to $500 million”.

Related: NVIDIA and Lambda (2025-09); Microsoft and Lambda (2025-11-03).

Macquarie Groupup to $500M—Signed
Anthropic
Details for Anthropic and Amazon Web Services, 2023-09-25

Amazon agreed to invest up to $4 billion in Anthropic, and AWS became Anthropic's primary cloud provider for mission-critical workloads, with access to AWS Trainium and Inferentia chips.

With Amazon. Chips: AWS Trainium, AWS Inferentia. Stated as “Amazon will invest up to $4 billion in Anthropic”.

Related: Anthropic and Amazon Web Services (2024-11-22); Anthropic and Amazon Web Services (2024-12-03); Anthropic and Amazon Web Services (2026-04-20).

Amazon Web Servicesup to $4B—Signed
CoreWeave
Details for CoreWeave and Magnetar Capital and Blackstone, 2023-08-03

CoreWeave secured a $2.3 billion debt facility led by Magnetar and Blackstone, committed to buying hardware for customer contracts it had already signed. Coatue, DigitalBridge, BlackRock, PIMCO, Carlyle and Great Elm also participated.

With Coatue, DigitalBridge, BlackRock, PIMCO, Carlyle, Great Elm. Stated as “a $2.3 billion debt facility”.

Related: CoreWeave and Blackstone (2024-05-17).

Magnetar Capital and Blackstone$2.3Bcontract value—Signed
Microsoft
Details for Microsoft and CoreWeave, 2023-06-01

CNBC reported that Microsoft agreed to spend potentially billions of dollars over multiple years on GPU cloud capacity from Nvidia-backed CoreWeave to help meet demand from OpenAI. Neither company disclosed terms at the time.

With OpenAI. Stated as “could be worth billions of dollars over multiple years”.

Related: OpenAI and Microsoft (2023-01-23).

CoreWeave——Reported
OpenAI
Details for OpenAI and Microsoft, 2023-01-23

Microsoft announced the third phase of its OpenAI partnership, a multiyear, multibillion-dollar investment under which Azure became OpenAI's exclusive cloud provider for research, products and API services. The cloud terms were changed in January 2025 and again in October 2025.

Stated as “multiyear, multibillion dollar investment”.

  • : Exclusivity on new capacity replaced by a Microsoft right of first refusal. Source
  • : OpenAI contracted an incremental $250B of Azure services and the right of first refusal ended. Source

Related: OpenAI and Microsoft (2025-01-21); OpenAI and Microsoft (2025-10-28).

Microsoft——Amended

How to read the stated values

Capacity is the power or unit count a source states; vaguer wording (“more than a gigawatt”) is left out of the column and kept in the deal’s details. The sites these deals build are in the buildout ledger, the markets that price their compute on the markets page, and the full ledger is open data at /deals.json.

Background reading: List of AI compute deals on AI Wiki. AI Wiki is run by the same team as AI Compute Tracker.