04Buildout· as of 2026-10-15

AI datacenter buildout

The gigawatt land-grab. Financial disclosures reviewed 2026-10-15; cluster ledger reviewed 2026-10-14. Companywide capex includes spending beyond AI.

Big-4 capex guidance · 2026

$732.5B

≈1.8× 2025 actuals · MSFT + GOOG + META + AMZN midpoints

NVIDIA DC revenue · FY27 Q2

$89.0B

~$360B/yr run-rate

Tracked frontier pipeline

~37 GW

Sum of planned capacity, clusters below

Largest single campus

Hyperion

Meta · up to 5 GW

Big-tech capital expenditure

US$B per calendar year (2026 = guidance midpoints)

Capital-expenditure chart awaiting interactive loadStatic chart frame · exact values in table view

Guidance reviewed Oct 2026; older actuals retained. Company definitions differ: Microsoft includes finance leases; Oracle’s FY27 estimate is NET cash capex and is not comparable with prior-year gross capex. See source notes below.

Exact values for Big-tech capital expenditure
Big-tech capital expenditure — exact values in tabular form
Company2023202420252026E
Amazon$52.7B$83.0B$131.8B$220.0B
Microsoft$41.2B$75.6B$118.0B$175.0B
Alphabet$32.3B$52.5B$91.4B$200.0B
Meta$28.1B$39.2B$72.2B$137.5B
Oracle$6.9B$21.2B$55.7B$70.0B

NVIDIA data-center revenue

US$B by fiscal quarter (FY ends late January)

NVIDIA revenue chart awaiting interactive loadStatic chart frame · exact values in table view

NVIDIA quarterly releases. Next-quarter guidance ~$108B total revenue, assuming zero China DC sales.

Exact values for NVIDIA data-center revenue
NVIDIA data-center revenue — exact values in tabular form
Fiscal quarterData-center revenue
FY24 Q1$4.28B
FY24 Q2$10.32B
FY24 Q3$14.51B
FY24 Q4$18.40B
FY25 Q1$22.56B
FY25 Q2$26.27B
FY25 Q3$30.77B
FY25 Q4$35.58B
FY26 Q1$39.11B
FY26 Q2$41.10B
FY26 Q3$51.20B
FY26 Q4$62.30B
FY27 Q1$75.20B
FY27 Q2$89.00B

Guidance sources and accounting basis

Frontier-scale clusters & campuses

26 sites · 9 operating · ~37 GW planned

Provenanced site ledger, surveyed Oct 2026. Power figures are IT load where trackers publish it and campus power where only the operator’s headline exists — open Provenance for each figure’s dated source.

Frontier-scale AI datacenters
Anthropic–Google TPU fleetest — estimated / secondary-source figure
Provenance for Anthropic–Google TPU fleet

Capacity program, not a single campus: >1 GW in 2026 plus 5 GW of next-gen TPU capacity (Google/Broadcom) from 2027. Anthropic calls that deal an expansion of its $50B US commitment, so it may overlap the Fluidstack rows, which carry no MW.

  • Planned power >1 GW of TPU capacity online in 2026 (expansion worth tens of billions) — Anthropic,
  • Planned power 5 GW of next-generation TPU capacity with Google and Broadcom, coming online from 2027 — Anthropic,
  • Accelerators Up to 1M Google TPUs under the Oct 2025 agreement — Anthropic,
  • Announced Google Cloud TPU expansion announced Oct 23, 2025 — Anthropic,
Anthropic · Google Cloud— → 6 GWBuilding
Hyperionest — estimated / secondary-source figure
Provenance for Hyperion

Planned figure is Meta’s 5 GW target, which the tracker says lacks concrete evidence at this site alone; it models ≈1.6 GW IT and first power in 2028.

  • Planned power Richland Parish expanding to 5GW of compute capacity; more than $50B invested — Meta,
  • Accelerators · est ≈469K NVIDIA Rubin chips projected for Q1 2028 (tracker estimate) — Epoch AI data-center directory,
  • Announced · est Meta’s Richland Parish data center announced December 2024 — Louisiana Economic Development,
Meta— → 5 GWBuilding
Jamnagar AI campusest — estimated / secondary-source figure
Provenance for Jamnagar AI campus

Reported 3 GW target — would be the world’s largest by capacity; $20–30B reported cost. Reliance itself says “multi-gigawatt”; construction had begun by Feb 2026 and the first 120 MW is due to be commissioned by end-2026.

Reliance Industries— → 3 GWBuilding
Stargate Doña Ana County (Project Jupiter)est — estimated / secondary-source figure
Provenance for Stargate Doña Ana County (Project Jupiter)

Power plan switched to an on-site Bloom fuel-cell microgrid (Apr 2026); planned figure is facility power (tracker-modeled IT ≈ 1.75 GW).

  • Planned power Up to 2.45 GW of installed Bloom fuel-cell capacity to power Project Jupiter (power supply, not IT load) — Oracle,
  • Planned power · est 1,750 MW IT (≈2.45 GW facility) at completion, Q4 2028 (tracker estimate) — Epoch AI data-center directory,
  • Accelerators · est ≈5.1M H100-equivalents projected at completion, Q4 2028 (tracker estimate) — Epoch AI data-center directory,
  • Announced Named in the five-new-Stargate-sites announcement — OpenAI,
OpenAI · Oracle · STACK— → 2.5 GWBuilding
Fairwater Wisconsinest — estimated / secondary-source figure
Provenance for Fairwater Wisconsin

“World’s most powerful AI datacenter” claim; first facility complete Jun 2026, campus path to ~2 GW by 2028.

  • Current power · est ≈369 MW IT live (tracker estimate) — Epoch AI data-center directory,
  • Planned power · est ≈2.26 GW IT projected by Q2 2028 (tracker estimate) — Epoch AI data-center directory,
  • Accelerators “Hundreds of thousands” of NVIDIA GPUs run as a single cluster of interconnected GB200 servers — Microsoft,
  • Accelerators · est ≈176K NVIDIA B200 installed (tracker estimate) — Epoch AI data-center directory,
  • Announced Fairwater Wisconsin unveiled Sep 2025 — Microsoft,
  • First power Equipment online and startup in April 2026; construction complete and fully operational Jun 23, 2026 — Microsoft,
Microsoft369 MW → 2.3 GWOperating
Project Rainierest — estimated / secondary-source figure
Provenance for Project Rainier

Flagship of the Amazon–Anthropic expansion (up to 5 GW, >$100B AWS commitment over 10 years). Live figure is tracker IT load; planned figure is Amazon’s 2.2 GW campus, which the tracker models as ≈1.9 GW IT by Q1 2028.

  • Current power · est ≈910 MW IT live (tracker estimate) — Epoch AI data-center directory,
  • Planned power Project Rainier in Northern Indiana—a 2.2-gigawatt data center campus — Amazon,
  • Accelerators · est ≈1,045K Trainium2 installed (tracker estimate) — Epoch AI data-center directory,
  • Accelerators Nearly half a million Trainium2 chips at activation, Oct 2025 — Amazon,
  • Accelerators Nearly 1 GW of Trainium2+3 capacity online across AWS by end-2026; up to 5 GW total — Anthropic,
  • Announced Project Rainier disclosed as an EC2 UltraCluster built with Anthropic, Dec 3, 2024 — Amazon (AWS press release),
  • First power AWS activates Project Rainier, now fully operational, Oct 2025 — Amazon,
Anthropic · AWS910 MW → 2.2 GWOperating
Colossus 2est — estimated / secondary-source figure
Provenance for Colossus 2

Spans Memphis, TN and Southaven, MS; a third building (projected ~Feb 2027) takes the site toward 2 GW of facility power. Anthropic also contracted GPU capacity here in 2026.

SpaceXAI (SpaceX, formerly xAI)946 MW → 2 GWOperating
Stargate Shackelford Countyest — estimated / secondary-source figure
Provenance for Stargate Shackelford County

Vantage “Frontier” campus; Vantage targets first delivery in H2 2026, while the tracker projects first IT load in 2027.

  • Planned power · est ≈2.0 GW planned (tracker estimate) — Epoch AI — Stargate US sites,
  • Accelerators · est ≈4.56M H100-equivalents projected at full build, Q4 2028 (Rubin-era; tracker estimate) — Epoch AI data-center directory,
  • Announced Named in the five-new-Stargate-sites announcement — OpenAI,
OpenAI · Oracle · Vantage— → 2 GWBuilding
Stargate Saline Townshipest — estimated / secondary-source figure
Provenance for Stargate Saline Township

Related Digital build southwest of Ann Arbor; announced Oct 2025, construction celebrated Jun 1, 2026 (first of three buildings then nearing completion).

OpenAI · Oracle · Related Digital— → 1.4 GWBuilding
Stargate Port Washington (Lighthouse)est — estimated / secondary-source figure
Provenance for Stargate Port Washington (Lighthouse)
OpenAI · Oracle · Vantage— → 1.3 GWBuilding
Stargate Abileneest — estimated / secondary-source figure
Provenance for Stargate Abilene

Flagship of the Stargate program — 6 of 8 buildings delivered by Sep 2026 (Oracle); planned figure is campus facility power (tracker-modeled IT ≈ 0.84 GW).

  • Current power · est 6 of 8 campus buildings, 618 MW and 75% of total capacity, delivered to the customer (Oracle Q1 FY27 call, Sep 10, 2026) — Oracle earnings call (The Motley Fool transcript),
  • Planned power · est 1.2 GW campus at completion (Q4 2026 target) — Epoch AI — Stargate US sites,
  • Accelerators · est 100.8K B200 + 302.4K B300 projected for Q4 2026 (403.2K total; tracker estimate) — Epoch AI data-center directory,
  • Announced Stargate program unveiled Jan 21, 2025, with the buildout “starting in Texas” — OpenAI,
  • First power First two buildings energized within a year of June 2024 groundbreaking — Crusoe,
OpenAI · Oracle · Crusoe618 MW → 1.2 GWOperating
Stargate Milam Countyest — estimated / secondary-source figure
Provenance for Stargate Milam County

SB Energy (SoftBank) builds and operates the site; its first building’s construction completion is filed for Oct 15, 2026 (Texas TDLR), with no energization announced yet.

  • Planned power OpenAI’s previously announced 1.2 GW data center site in Milam County — SB Energy,
  • Accelerators · est ≈2.5M H100-equivalents of compute projected — Epoch AI — Stargate US sites,
  • Announced Named in the five-new-Stargate-sites announcement — OpenAI,
OpenAI · SB Energy— → 1.2 GWBuilding
Prometheusest — estimated / secondary-source figure
Provenance for Prometheus

Meta’s ~1 GW cluster target; nuclear supply deals (TerraPower, Oklo, Vistra) signed Jan 2026. The Oct 2026 tracker re-model (B300 chips) lowered the live estimate; the site did not shrink.

Meta471 MW → 1 GWOperating
El Paso campusest — estimated / secondary-source figure
Provenance for El Paso campus

$14B venture with BlackRock (80/20); Meta sole initial occupant, operations expected 2028.

  • Planned power 1 GW of compute capacity, operating from 2028 — Meta,
  • Accelerators AI-optimized data center; chip platform not yet disclosed — Meta,
  • Announced Groundbreaking announced Oct 15, 2025 — Meta,
Meta · BlackRock— → 1 GWBuilding
Stargate UAEest — estimated / secondary-source figure
Provenance for Stargate UAE

1 GW cluster anchoring the 5 GW UAE–US AI campus. The first 200 MW was due in Q3 2026 (Mubadala, Dec 2025); no go-live had been announced by mid-Oct 2026, and Sep 2026 press reports describe a hardened redesign.

  • Planned power 1 GW Stargate UAE cluster within a 5 GW campus — OpenAI,
  • Accelerators NVIDIA Grace Blackwell GB300 systems — OpenAI,
  • Announced Stargate UAE announced May 22, 2025 — OpenAI,
  • Status First 200 MW phase progressing toward planned 2026 delivery — G42,
  • Status · est Under construction; first 200 MW (Buildings 1–2) projected operational by Dec 2026 (tracker estimate) — Epoch AI data-center directory,
G42 · OpenAI · Oracle— → 1 GWBuilding
Visakhapatnam AI hubest — estimated / secondary-source figure
Provenance for Visakhapatnam AI hub

$15B for 2026–2030, Google’s largest investment in India to date; ground broken Apr 28, 2026 and operations expected in 2028. Petitions against its environmental clearances are pending (Oct 2026 press reports).

  • Planned power · est Gigawatt-scale data center campus (US$15B, 2026–2030) — Adani Group,
  • Accelerators Google AI hub infrastructure; accelerator mix not disclosed — Google Cloud,
  • Announced Adani–Google partnership announced Oct 14, 2025 — Adani Group,
  • Status Google broke ground on the Visakhapatnam AI hub Apr 28, 2026 — Google Cloud,
Google · AdaniConneX · Airtel (Nxtra)— → 1 GWBuilding
Fairwater Atlantaest — estimated / secondary-source figure
Provenance for Fairwater Atlanta

QTS-built, grid-only design (no UPS/gen-sets); linked with Wisconsin into one “AI superfactory” WAN.

Microsoft636 MWOperating
HUMAIN AI factoriesest — estimated / secondary-source figure
Provenance for HUMAIN AI factories

PIF-backed sovereign AI buildout; capacity target “up to 500 MW” across factories in the Kingdom. A Sep 2026 secondary report of a live NVIDIA B300 cloud awaits a HUMAIN or NVIDIA primary source.

  • Accelerators Up to 600,000 NVIDIA GPUs, including GB300, over three years across Saudi Arabia and the US — HUMAIN (PR Newswire),
  • Planned power AI factories with a projected capacity of up to 500 MW — NVIDIA,
  • Accelerators First phase: an 18,000-GPU NVIDIA GB300 supercomputer — NVIDIA,
  • Announced HUMAIN–NVIDIA partnership announced May 13, 2025 — NVIDIA,
HUMAIN · NVIDIA— → 500 MWBuilding
Stargate Argentinaest — estimated / secondary-source figure
Provenance for Stargate Argentina

Letter of intent only (up to $25B), with OpenAI as a prospective offtaker of a Sur Energy joint venture; the project had not been presented to the government or its RIGI investment regime as of late May 2026.

  • Planned power Up to 500 MW under the OpenAI–Sur Energy letter of intent — Sur Energy,
  • Accelerators · est Capable of hosting “the next generation of AI computing”; chips unspecified — Sur Energy,
  • Announced OpenAI–Sur Energy LOI announced Oct 10, 2025 — Sur Energy,
  • Status · est LOI only; not presented to the government or RIGI as of late May 2026 — Buenos Aires Times,
Sur Energy · OpenAI— → 500 MWAnnounced
Polaris Forge 1
Provenance for Polaris Forge 1

Applied Digital campus fully leased to CoreWeave across three buildings (~$11B contracted revenue); Buildings 1–2 (250 MW) live by Oct 2026, third 150 MW building under construction.

  • Current power 250 MW fully operational critical IT load (Buildings 1–2) — Applied Digital,
  • Planned power 400 MW critical IT load contracted at full buildout — Applied Digital,
  • Accelerators · est Leased to CoreWeave; GPU models not disclosed — Applied Digital,
  • First power Phase I (first 50 MW) ready for service Oct 2025; Building 1 fully energized Nov 24, 2025 — Applied Digital,
CoreWeave · Applied Digital250 MW → 400 MWOperating
Omaha TPU campusest — estimated / secondary-source figure
Provenance for Omaha TPU campus

Google’s flagship disclosed-scale TPU training campus; expansion projected through Q3 2028.

Google237 MW → 395 MWOperating
Colossus 1est — estimated / secondary-source figure
Provenance for Colossus 1

First ~100K H100 built in 122 days in 2024; a grid link upgraded toward 150 MW plus on-site gas turbines and Megapacks. Since May 2026 all of its compute capacity is contracted to Anthropic.

  • Current power · est All of Colossus 1’s compute capacity contracted to Anthropic: more than 300 MW (over 220,000 NVIDIA GPUs) — Anthropic,
  • Current power · est ≈340 MW IT (≈425 MW facility), unchanged since Nov 2025 (tracker estimate) — Epoch AI data-center directory,
  • Accelerators · est 230K GPUs: 150K H100, 50K H200, 30K GB200 (Musk on X, Sep 25, 2026) — Tom’s Hardware (quoting Elon Musk on X),
  • First power · est 100K H100s online Sep 2, 2024 (tracker timeline) — Epoch AI data-center directory,
  • First power · est Initial ~100K-H100 cluster built in 122 days and live in mid-to-late 2024; the grid link (~8 MW at first, upgraded toward 150 MW) was supplemented by temporary gas turbines and Tesla Megapacks — Wikipedia — Colossus (data center),
SpaceXAI (SpaceX, formerly xAI)300 MWOperating
Stargate Lordstownest — estimated / secondary-source figure
Provenance for Stargate Lordstown

SoftBank/Foxconn advanced data-center design; ground broken 2025 and targeted operational 2026 (Sep 2025), while the tracker now projects Q1 2027.

  • Planned power · est <0.3 GW modeled (tracker estimate) — Epoch AI — Stargate US sites,
  • Accelerators · est ≈546K H100-equivalents (≈61.5K Rubin) projected for Q1 2027 (tracker estimate) — Epoch AI data-center directory,
  • Announced Named in the five-new-Stargate-sites announcement; ground already broken — OpenAI,
OpenAI · SoftBank · Foxconn— → 300 MWBuilding
Nscale Narvik (announced as Stargate Norway)est — estimated / secondary-source figure
Provenance for Nscale Narvik (announced as Stargate Norway)

Hydropower-fed campus, now run solely by Nscale (the Aker joint venture was folded in, Mar 2026) with Microsoft as offtaker; OpenAI reportedly left lease talks (Apr 2026). Ambition to add a further 290 MW beyond the initial 230 MW.

  • Planned power 230 MW initial capacity (ambition for +290 MW) — Nscale,
  • Accelerators Aker-Nscale joint venture to deliver ~52,000 NVIDIA GB300 GPUs to Microsoft from Narvik (multi-year agreement) — Nscale,
  • Accelerators More than 30,000 NVIDIA Rubin GPUs added at the 230 MW Narvik campus for Microsoft, in 2027 — Nscale,
  • Status · est Under construction; no buildings operational at the Jul 2026 imagery; 92 MW projected by end-2026 (tracker estimate) — Epoch AI data-center directory,
  • Announced Nscale/Aker/OpenAI announce Stargate Norway Jul 31, 2025 — Nscale,
Nscale (Microsoft offtake)— → 230 MWBuilding
Fluidstack build (Texas)est — estimated / secondary-source figure
Provenance for Fluidstack build (Texas)

Part of Anthropic’s $50B US datacenter program with Fluidstack (Texas, New York and more sites to come); no per-site MW published.

  • Announced $50B US datacenter investment with Fluidstack; Texas and New York first, online through 2026 — Anthropic,
  • Accelerators Custom-built facilities; Fluidstack picked for its ability to deliver “gigawatts of power” (chips undisclosed) — Anthropic,
Anthropic · Fluidstack—Building
Fluidstack build (New York)est — estimated / secondary-source figure
Provenance for Fluidstack build (New York)

Part of Anthropic’s $50B US datacenter program with Fluidstack (Texas, New York and more sites to come); no per-site MW published.

  • Announced $50B US datacenter investment with Fluidstack; Texas and New York first, online through 2026 — Anthropic,
  • Accelerators Custom-built facilities; Fluidstack picked for its ability to deliver “gigawatts of power” (chips undisclosed) — Anthropic,
Anthropic · Fluidstack—Building

The contracts that pay for these campuses, from cloud capacity to chips, leases and power, are in the compute deals ledger.