Jamnagar AI campus AI datacenter

Reliance Industries · Jamnagar, Gujarat, India. The ledger records it as under construction, with 3 GW planned. Every figure below traces to a dated public source.

Ledger figures

Operator
Reliance Industries
Location
Jamnagar, Gujarat, India
Status
Under construction
Current power
No public figure
Planned power
3 GWest — estimated / secondary-source figureBasis not specified
Accelerators
NVIDIA GB300 (initial fleet; >75K H100-eq for inference)
Announced
2024-08-29
First power
No public date
Target online
2026

Reported 3 GW target — would be the world’s largest by capacity; $20–30B reported cost. Reliance itself says “multi-gigawatt”; construction had begun by Feb 2026 and the first 120 MW is due to be commissioned by end-2026.

Current and planned figures may use different power bases. Planned power is the end state, not additional capacity to add to the current figure. An unspecified basis remains unknown. A figure marked est rests on at least one source other than the operator’s own announcement.

Sources behind each figure