Buildout · frontier site· cluster ledger evidence retained through 2026-10-25

Stargate Milam County AI datacenter

OpenAI · SB Energy · Texas. The ledger records it as under construction, with 1.2 GW planned. Every figure below traces to a dated public source.

Ledger figures

Operator
OpenAI · SB Energy
Location
Texas
Status
Under construction
Current power
No public figure
Planned power
1.2 GWBasis not specified
Accelerators
GB300-era NVIDIA (≈2.5M H100-equivalents projected)
Announced
2025-09-23
First power
No public date
Target online
2028

SB Energy (SoftBank) builds and operates the site; its first building’s construction completion is filed for Oct 15, 2026 (Texas TDLR), with no energization announced yet.

Current and planned figures may use different power bases. Planned power is the end state, not additional capacity to add to the current figure. An unspecified basis remains unknown. A figure marked est rests on at least one source other than the operator’s own announcement.

Sources behind each figure

  • Planned power OpenAI’s previously announced 1.2 GW data center site in Milam County — SB Energy,
  • Accelerators · est ≈2.5M H100-equivalents of compute projected — Epoch AI — Stargate US sites,
  • Announced Named in the five-new-Stargate-sites announcement — OpenAI,
  • Target online · est 857 MW IT projected for Q4 2028; all buildings finished and site fully operational projected Dec 31, 2028, a conservative estimate (tracker estimate) — Epoch AI data-center directory,

Connected labs, contracts and evidence

Each link names its recorded relationship. Sharing a source does not establish that a contract funds this site; a lab reference does not assign the site’s whole capacity to that lab.

← Every tracked site, capex and NVIDIA revenue

Background reading: Stargate Project on AI Wiki. AI Wiki is run by the same team as AI Compute Tracker.