Stargate Lordstown AI datacenter
OpenAI · SoftBank · Foxconn · Lordstown, Ohio. The ledger records it as under construction, with 300 MW planned. Every figure below traces to a dated public source.
Ledger figures
- Operator
- OpenAI · SoftBank · Foxconn
- Location
- Lordstown, Ohio
- Status
- Under construction
- Current power
- No public figure
- Planned power
- 300 MWest — estimated / secondary-source figureBasis not specified
- Accelerators
- NVIDIA Rubin (≈0.55M H100-equivalents projected)
- Announced
- 2025-09-23
- First power
- No public date
- Target online
- 2027
SoftBank/Foxconn advanced data-center design; ground broken 2025 and targeted operational 2026 (Sep 2025), while the tracker now projects Q1 2027.
Current and planned figures may use different power bases. Planned power is the end state, not additional capacity to add to the current figure. An unspecified basis remains unknown. A figure marked est rests on at least one source other than the operator’s own announcement.
Sources behind each figure
- Planned power · est <0.3 GW modeled (tracker estimate) — Epoch AI — Stargate US sites,
- Accelerators · est ≈546K H100-equivalents (≈61.5K Rubin) projected for Q1 2027 (tracker estimate) — Epoch AI data-center directory,
- Announced Named in the five-new-Stargate-sites announcement; ground already broken — OpenAI,
- Target online · est ≈546K H100-equivalents (≈61.5K Rubin) projected for Q1 2027 (tracker estimate); OpenAI had said in Sep 2025 the site was expected operational in 2026 — Epoch AI data-center directory,
Connected labs, contracts and evidence
Each link names its recorded relationship. Sharing a source does not establish that a contract funds this site; a lab reference does not assign the site’s whole capacity to that lab.
- OpenAI and Oracle →Cites the same source document ·
Background reading: Stargate Project on AI Wiki. AI Wiki is run by the same team as AI Compute Tracker.