Buildout · frontier site· cluster ledger evidence retained through 2026-10-25
Stargate Shackelford County AI datacenter
OpenAI · Oracle · Vantage · Texas. The ledger records it as under construction, with 2 GW planned. Every figure below traces to a dated public source.
Ledger figures
- Operator
- OpenAI · Oracle · Vantage
- Location
- Texas
- Status
- Under construction
- Current power
- No public figure
- Planned power
- 2 GWest — estimated / secondary-source figureBasis not specified
- Accelerators
- NVIDIA Rubin-era (≈4.6M H100-equivalents projected)
- Announced
- 2025-09-23
- First power
- No public date
- Target online
- 2028
Vantage “Frontier” campus; Vantage targets first delivery in H2 2026, while the tracker projects first IT load in 2027.
Current and planned figures may use different power bases. Planned power is the end state, not additional capacity to add to the current figure. An unspecified basis remains unknown. A figure marked est rests on at least one source other than the operator’s own announcement.
Sources behind each figure
- Planned power · est ≈2.0 GW planned (tracker estimate) — Epoch AI — Stargate US sites,
- Accelerators · est ≈4.56M H100-equivalents projected at full build, Q4 2028 (Rubin-era; tracker estimate) — Epoch AI data-center directory,
- Announced Named in the five-new-Stargate-sites announcement — OpenAI,
- Target online · est ≈4.56M H100-equivalents projected at full build, Q4 2028 (Rubin-era; tracker estimate) — Epoch AI data-center directory,
Connected labs, contracts and evidence
Each link names its recorded relationship. Sharing a source does not establish that a contract funds this site; a lab reference does not assign the site’s whole capacity to that lab.