Ridgeland campus AI datacenter
Amazon (AWS) · Ridgeland, Mississippi. The ledger records it as operating, with 228 MW current and 840 MW planned. Every figure below traces to a dated public source.
Ledger figures
- Operator
- Amazon (AWS)
- Location
- Ridgeland, Mississippi
- Status
- Operating
- Current power
- 228 MWest — estimated / secondary-source figureIT load
- Planned power
- 840 MWest — estimated / secondary-source figureIT load
- Accelerators
- AWS Trainium (Trainium2, tracker estimate)
- Announced
- No public date
- First power
- No public date
- Target online
- 2028-09
Fourteen-building Amazon campus; the tracker lists Anthropic and Project Rainier as speculative links. The planned figure assumes Buildings 6–14 start by Jul 2026 and finish by Sep 2028 (tracker estimate); Amazon has published no MW for this site.
Current and planned figures may use different power bases. Planned power is the end state, not additional capacity to add to the current figure. An unspecified basis remains unknown. A figure marked est rests on at least one source other than the operator’s own announcement.
Sources behind each figure
- Current power · est ≈228 MW IT, Buildings 1–4 operational at the May 15, 2026 observation (tracker estimate) — Epoch AI data-center directory,
- Planned power · est ≈840 MW IT projected by Sep 29, 2028 with Buildings 6–14 operational (tracker estimate) — Epoch AI data-center directory,
- Accelerators · est Amazon’s own AI chips, estimated to be Trainium2 (tracker estimate) — Epoch AI data-center directory,
- Target online · est ≈840 MW IT projected by Sep 29, 2028 (tracker estimate) — Epoch AI data-center directory,
Background reading: Amazon Web Services on AI Wiki. AI Wiki is run by the same team as AI Compute Tracker.