Ridgeland campus AI datacenter

Amazon (AWS) · Ridgeland, Mississippi. The ledger records it as operating, with 228 MW current and 840 MW planned. Every figure below traces to a dated public source.

Ledger figures

Operator
Amazon (AWS)
Location
Ridgeland, Mississippi
Status
Operating
Current power
228 MWest — estimated / secondary-source figureIT load
Planned power
840 MWest — estimated / secondary-source figureIT load
Accelerators
AWS Trainium (Trainium2, tracker estimate)
Announced
No public date
First power
No public date
Target online
2028-09

Fourteen-building Amazon campus; the tracker lists Anthropic and Project Rainier as speculative links. The planned figure assumes Buildings 6–14 start by Jul 2026 and finish by Sep 2028 (tracker estimate); Amazon has published no MW for this site.

Current and planned figures may use different power bases. Planned power is the end state, not additional capacity to add to the current figure. An unspecified basis remains unknown. A figure marked est rests on at least one source other than the operator’s own announcement.