04BBuildout · frontier site· cluster ledger evidence retained through 2026-10-25

Highridge Business Park AI factory AI datacenter

Nebius · Butler Township, Pennsylvania. The ledger records it as announced, with 1.2 GW planned. Every figure below traces to a dated public source.

Ledger figures

Operator
Nebius
Location
Butler Township, Pennsylvania
Status
Announced
Current power
No public figure
Planned power
1.2 GWBasis not specified
Accelerators
Nebius AI cloud (chips undisclosed)
Announced
2026-05-13
First power
No public date
Target online
No public date

New Nebius-owned AI factory in Schuylkill County (Highridge Business Park); Nebius’s undated project page targets 260 MW by Oct 2027 and 1.2 GW at full buildout.

Current and planned figures may use different power bases. Planned power is the end state, not additional capacity to add to the current figure. An unspecified basis remains unknown. A figure marked est rests on at least one source other than the operator’s own announcement.

Sources behind each figure

  • Planned power Secured up to 1.2 GW of power and land for a new, owned AI factory at a site in Pennsylvania — Nebius,
  • Accelerators New, owned AI factory; hardware not specified — Nebius,
  • Announced Pennsylvania site disclosed with Nebius’s Q1 2026 results, May 13, 2026 — Nebius,
← Every tracked site, capex and NVIDIA revenue