Buildout · frontier site· cluster ledger evidence retained through 2026-10-25

Project Rainier AI datacenter

Anthropic · AWS · New Carlisle, Indiana. The ledger records it as operating, with 1 GW current and 2.2 GW planned. Every figure below traces to a dated public source.

Ledger figures

Operator
Anthropic · AWS
Location
New Carlisle, Indiana
Status
Operating
Current power
1 GWest — estimated / secondary-source figureIT load
Planned power
2.2 GWCampus / facility power
Accelerators
~1.05M Trainium2 live (tracker estimate); ~1 GW Trainium2+3 across AWS by end-2026
Announced
2024-12-03
First power
2025-10
Target online
2028

Flagship of the Amazon–Anthropic expansion (up to 5 GW, >$100B AWS commitment over 10 years). Live figure is tracker IT load (Buildings 1–18 at the Oct 19, 2026 observation); planned figure is Amazon’s 2.2 GW campus, which the tracker models as ≈1.9 GW IT by Q1 2028.

Current and planned figures may use different power bases. Planned power is the end state, not additional capacity to add to the current figure. An unspecified basis remains unknown. A figure marked est rests on at least one source other than the operator’s own announcement.

Delivery evidence and customer use

Selected contract tranches reviewed . An announced target stays a target until a source confirms delivery. These records do not change the campus capacity figures or form an operating-capacity total.

How to compare capacity and delivery →

Sources behind each figure

  • Current power · est ≈910 MW IT live (tracker estimate) — Epoch AI data-center directory,
  • Current power · est ≈1,037 MW IT live, Buildings 17–18 now operational, at the Oct 19, 2026 observation (tracker estimate) — Epoch AI data-center directory,
  • Planned power Project Rainier in Northern Indiana—a 2.2-gigawatt data center campus — Amazon,
  • Accelerators · est ≈1,045K Trainium2 installed (tracker estimate) — Epoch AI data-center directory,
  • Accelerators Nearly half a million Trainium2 chips at activation, Oct 2025 — Amazon,
  • Accelerators Nearly 1 GW of Trainium2+3 capacity online across AWS by end-2026; up to 5 GW total — Anthropic,
  • Announced Project Rainier disclosed as an EC2 UltraCluster built with Anthropic, Dec 3, 2024 — Amazon (AWS press release),
  • First power AWS activates Project Rainier, now fully operational, Oct 2025 — Amazon,
  • Target online · est In Q1 2028, projected to rise to 1,925 MW IT power (Buildings 19–32 operational; tracker estimate) — Epoch AI data-center directory,

Connected labs, contracts and evidence

Each link names its recorded relationship. Sharing a source does not establish that a contract funds this site; a lab reference does not assign the site’s whole capacity to that lab.

← Every tracked site, capex and NVIDIA revenue

Background reading: Project Rainier on AI Wiki. AI Wiki is run by the same team as AI Compute Tracker.