River Bend campus AI datacenter

Anthropic · Fluidstack · Hut 8 · Louisiana. The ledger records it as under construction, with 245 MW planned. Every figure below traces to a dated public source.

Ledger figures

Operator
Anthropic · Fluidstack · Hut 8
Location
Louisiana
Status
Under construction
Current power
No public figure
Planned power
245 MWIT load
Accelerators
Fluidstack-operated clusters for Anthropic (chips undisclosed)
Announced
2025-12-17
First power
No public date
Target online
2027

Tranche 1 of a Hut 8–Anthropic–Fluidstack partnership of at least 245 MW and up to 2,295 MW: 245 MW of IT capacity (330 MW utility) at River Bend, a right of first offer on up to 1,000 MW more IT capacity at River Bend, and up to 1,050 MW optional at other Hut 8 sites. Planned figure is the firm tranche only. May overlap Anthropic’s $50B Fluidstack program (Texas and New York rows).

Current and planned figures may use different power bases. Planned power is the end state, not additional capacity to add to the current figure. An unspecified basis remains unknown. A figure marked est rests on at least one source other than the operator’s own announcement.

Sources behind each figure

  • Planned power Tranche 1: 245 MW of IT capacity supported by 330 MW of utility capacity at River Bend; ROFO on up to 1,000 MW of additional IT capacity there, subject to expanded power — Hut 8,
  • Accelerators High-performance clusters operated by Fluidstack for Anthropic; chips not named — Hut 8,
  • Announced Hut 8 announces AI infrastructure partnership with Anthropic and Fluidstack, Dec 17, 2025 — Hut 8,
  • Status Anthropic to bring additional capacity online by early 2027 (River Bend target in the release’s forward-looking statements) — Hut 8,
  • Target online Anthropic to bring additional capacity online by early 2027 — Hut 8,

Connected labs, contracts and evidence

Each link names its recorded relationship. Sharing a source does not establish that a contract funds this site; a lab reference does not assign the site’s whole capacity to that lab.