Buildout · frontier site· cluster ledger evidence retained through 2026-10-25
Visakhapatnam AI hub AI datacenter
Google · AdaniConneX · Airtel (Nxtra) · Visakhapatnam, Andhra Pradesh, India. The ledger records it as under construction, with 1 GW planned. Every figure below traces to a dated public source.
Ledger figures
- Operator
- Google · AdaniConneX · Airtel (Nxtra)
- Location
- Visakhapatnam, Andhra Pradesh, India
- Status
- Under construction
- Current power
- No public figure
- Planned power
- 1 GWest — estimated / secondary-source figureBasis not specified
- Accelerators
- Google AI infrastructure (accelerators undisclosed)
- Announced
- 2025-10-14
- First power
- No public date
- Target online
- 2028-07
$15B for 2026–2030, Google’s largest investment in India to date; ground broken Apr 28, 2026 and operations expected in 2028. Petitions against its environmental clearances are pending (Oct 2026 press reports).
Current and planned figures may use different power bases. Planned power is the end state, not additional capacity to add to the current figure. An unspecified basis remains unknown. A figure marked est rests on at least one source other than the operator’s own announcement.
Sources behind each figure
- Planned power · est Gigawatt-scale data center campus (US$15B, 2026–2030) — Adani Group,
- Accelerators Google AI hub infrastructure; accelerator mix not disclosed — Google Cloud,
- Announced Adani–Google partnership announced Oct 14, 2025 — Adani Group,
- Status Google broke ground on the Visakhapatnam AI hub Apr 28, 2026 — Google Cloud,
- Target online · est The project is expected to be completed by July 2028 (publication's own reporting, unattributed) — Business Today,