04BBuildout · frontier site· cluster ledger evidence retained through 2026-10-25

Abilene AI factory expansion (Microsoft) AI datacenter

Crusoe · Microsoft · Abilene, Texas. The ledger records it as under construction, with 900 MW planned. Every figure below traces to a dated public source.

Ledger figures

Operator
Crusoe · Microsoft
Location
Abilene, Texas
Status
Under construction
Current power
No public figure
Planned power
900 MWBasis not specified
Accelerators
Next-generation AI silicon (chips unspecified)
Announced
2026-03-27
First power
No public date
Target online
2027

New 900 MW campus beside Stargate Abilene, built to support Microsoft AI workloads: two buildings, each designed for 336 MW of critical IT load, plus an on-site power plant. Crusoe says the combined Abilene site reaches ~2.1 GW; first building to be energized mid-2027.

Current and planned figures may use different power bases. Planned power is the end state, not additional capacity to add to the current figure. An unspecified basis remains unknown. A figure marked est rests on at least one source other than the operator’s own announcement.

Sources behind each figure

  • Planned power The 900 MW site: two new buildings, each designed to deliver 336 MW of critical IT load, plus an on-site power plant; Abilene site to reach ~2.1 GW in total — Crusoe,
  • Accelerators Purpose-built for “next-generation AI silicon”; no chip named — Crusoe,
  • Announced Crusoe announces a new 900 MW AI factory campus in Abilene to support Microsoft AI infrastructure, Mar 27, 2026 — Crusoe,
  • Status Land clearing and site preparation underway; first building expected to be energized in mid-2027 — Crusoe,
  • Target online First building expected to be energized in mid-2027 — Crusoe,