04BBuildout · frontier site· cluster ledger evidence retained through 2026-10-25

Cedar Rapids campus AI datacenter

QTS (tenant undisclosed) · Cedar Rapids, Iowa. The ledger records it as under construction, with 1.1 GW planned. Every figure below traces to a dated public source.

Ledger figures

Operator
QTS (tenant undisclosed)
Location
Cedar Rapids, Iowa
Status
Under construction
Current power
No public figure
Planned power
1.1 GWest — estimated / secondary-source figureIT load
Accelerators
≈3.67M H100-equivalents projected for Q4 2027 (tracker estimate)
Announced
No public date
First power
No public date
Target online
2027

Seven-building campus; the tracker lists the owner as unknown, notes that its Phase 1 power estimate matches a 616 MW load request filed by a QTS shell company, and projects Buildings 1–3 (≈448 MW IT) operational by Nov 2026. No operator MW figure published.

Current and planned figures may use different power bases. Planned power is the end state, not additional capacity to add to the current figure. An unspecified basis remains unknown. A figure marked est rests on at least one source other than the operator’s own announcement.

Sources behind each figure

  • Planned power · est ≈1,133 MW IT projected for Q4 2027 once Buildings 4–7 are operational; ≈448 MW IT by Nov 15, 2026 (tracker estimate) — Epoch AI data-center directory,
  • Accelerators · est ≈3,669K H100-equivalents projected for Q4 2027; chip model not named (tracker estimate) — Epoch AI data-center directory,
  • Status · est Under construction: Buildings 1–3 shells complete, 4–6 far along, Building 7 foundation underway at the May 7, 2026 imagery; none operational (tracker estimate) — Epoch AI data-center directory,
  • Target online · est ≈1,133 MW IT projected for Q4 2027 (tracker estimate) — Epoch AI data-center directory,